Thursday, March 31, 2011

Lessons Not Learned


Nuclear Energy Institute Report On Japan's Nuclear Reactors, March 30, 2011 (12 PM EDT)
WEDNESDAY, 30 MARCH 2011 12:44 PRESS RELEASE LATEST NATIONAL NEWS

Washington, D.C.--(ENEWSPF)--March 30, 2011 - UPDATE AS OF 12 P.M. EDT.

Operators of nuclear power stations in Japan have been urged to ensure their facilities have emergency power sources.

Industry Minister Banri Kaieda Wednesday attributed the nuclear emergency in Japan to the loss of cooling systems at the Fukushima Daiichi nuclear power plant, the Japan Atomic Industry Forum reported. He told utility companies they should have mobile generators on hand to cool their nuclear reactors as an added safety measure.

......

Ah so! Leave it to our politicians.

And what will we do with these mobile generators?

We already have redundant emergency diesel generators in place, all damaged along with the equipment for which they're to power!

What are they to be connected to when all switchgear is water damaged?

What will they power? All required emergency electric motor driven pumps have been water damaged.

What, what, what?

They appear to be of the same ilk as our Main [Lame] Stream Press!


Background




















Shortly before 3 pm on the afternoon of Friday, March 11, a massive earthquake of approximately 9.0 magnitude struck offshore of Japan.

At the Fukushima Daichi plant, Units 1, 2 and 3 were in operation. The other three units were in various conditions of maintenance shutdown. As designed these three reactors shutdown automatically in response to the earthquake loads. Although, this earthquake exceeded by a large margin, the earthquake accelerations for which the reactors were designed, it appears that no adverse affect resulted.



1 Core with fuel rods
3 Equipment pool
5 Fuel storage pool; spent fuel area
8 Reactor pressure vessel
10 Secondary concrete shield wall
11 Free standing steel drywell
16 Vent header
17 Downcomer pipe
18 Water (wetwell)
20 Basement
21 Reactor building
22 Refuelling platform
24 Pressure supression chamber (runs in a torus around the reactor)
25 Vent (81 inch diameter)
26 Crane
27 Spent Fuel
29 Feedwater pipe
30 Steam pipe (to turbine-generator)
31 Control rod drives
39 Control rods
40 Steam separators (water normally goes to this level)
41 Steam dryer

The earthquake also caused the loss of electrical power from the national electrical grid. As a result, the redundant emergency diesel generators were activated on loss of external power which were provided to power all required emergency loads. Note, two full capacity diesel generator units are required at nuclear plants as required by the Single Failure Criterion design requirement. This requires that all emergency functions be available assuming a single failure of any given component.

Simultaneously, the emergency steam turbine driven feedwater pump was activated, providing feedwater cooling to the reactor vessels of units 1, 2 & 3.

Flowing through the reactor core fuel elements, this water was turned to steam by the residual heat remaining in the fuel rods. This steam, in turn, was directed downward into the torus water pool, where it was condensed.

Some 15 minutes later, The tsunami unleashed by the earthquake struck the Fukushima facility flooding out the emergency diesels, the electrical switchgear, and all the required electrical driven emergency pump motors.

With the loss of power from the grid and the damage to the diesel generators, the plant was now totally without power in which to drive emergency equipment. The only remaining emergency function remaining was the steam-driven pump which would only be functional for a few hours when the steam pressure had been reduced below working pressure.

At this time, emergency cooling water pumps should have been activated, but, had no electrical power available to power them, however, this would have been to no avail, as they had been damaged by the flooding waters.

Subsequently, without electric power, without cooling, the pressure within the nuclear units began to rise. This pressure buildup is the result of residual decay heat causing the coolant, which is not being circulated, to evaporate

The central problem behind almost every hurdle faced by the workers at the Fukushima nuclear power plant has been – and remains – a lack of power supply. Since electricity was knocked out by the Tsunami it has been impossible to run the pumps that cool the reactor cores and circulate water around storage pools used to keep spent fuel rods cooled.



Monday, March 28, 2011

Tsunami Aftermath

Here are three pictures which vividly portray the extent of the flooding caused by the earthquake induced Tsaunami.

Now, visualize the extend of the damage which occurred at the damaged reactors.

Like all Western nation reactor plants, these reactors were designed for a Tsaunami greater than ever recorded with the large margin given for uncertanties. In this case, they were designed for Tsaumi flooding of approximately 16 feet. We are now advised that the plant saw a water level of about 45 feet.















Sunday, March 27, 2011

Tsunami



Among the natural phenomenon for which these plants were built, was an earthquake induced Tsunami.

Along some coastal areas of Japan where population density is high, Tsunami walls are extensively built as Tsunami protection. Japan is the more prominent country which has used tsunami walls to have protection against locally generated tsunami. These walls are of 4.5 metres. Theses walls are also designed to redirect water in the event of a Tsunami facilitating floodgates and channels.

Variations in height of protection in Japan varied, some up to 30 feet which appears to be based on local topographic features.

At these reactors, a design of about 16 feet was provided. This height was considered well above any conceivable scenerio. The actual wall estimated at the plant was about 45 feet.

Obviously, it's back to the drawing boards.

I understand that the San Onofre reactors at San Clemente are designed for a Tsunami of 30 feet. News to me.